Home
Calendar
ISS
Expedition 36
Expedition 35
ISS Mission Archive
MSL
MSL Mission Updates 6
MSL Science Reports
MSL Rover Information
MSL Science Instruments
MSL Gallery
Juno
Juno Mission Updates 2013
NuSTAR
NuSTAR Mission Updates
RBSP
RBSP Mission Updates
IRIS
IRIS Mission Updates
IRIS Spacecraft and Instruments
IRIS Mission Design
IRIS Science Overview
Commercial
Arianespace
>
Ariane 5
Soyuz Kourou
Vega
SpaceX
United Launch Alliance
Orbital Sciences
International Launch Services
Sea Launch Missions
CCDev
Russia
China
Japan
Entry
Re-Entry May 2013
Other
Launch Vehicle Library
India
NPP
Shuttle Retirement Updates 3
Shuttle
SLS Orion
Phobos Grunt
Archive
Search
About
Share
|
Soyuz FG Generic Countdown Timeline
Time
Event
L-34:00:00
Tanking Preparations
L-08:00:00
Final Countdown commences
Soyuz Systems Checks
L-06:00:00
Battery Installation in Booster
L-05:30:00
Sate Commission Meeting
L-05:15:00
Crew Arrives at Site 254
L-05:00:00
Propellant Loading
L-04:20:00
Crew dons Sokol Suits
L-04:00:00
Liquid Oxygen loading complete
L-03:40:00
Crew reports to Delegations
L-03:00:00
Tank Cars depart
L-02:40:00
Crew arrives at Launch Site
L-02:30:00
Crew Ingress
L-02:00:00
Hatch Closure
L-01:45:00
Sokol Air Flow Initiation
Soyuz Spacecraft pressurization
Soyuz Systems Checks
Launcher Systems Checks
L-01:30:00
Internal Soyuz Hatch Pressure Checks
Communication System Activation
L-01:00:00
Guidance System Acitvation
Launch Pad Evacuation
L-00:45:00
Flight Computer Software Load
Service Tower Retraction (Service Structure Halves)
L-00:40:00
Sokol Pressure Verification
L-00:30:00
Launch Command Power Activation
SAS Launch Abort System Activation
L-00:25:00
Removal of Service Towers
L-00:15:00
Sokol Checks complete
Launch Pad clear
Escape System in Auto Mode
L-00:10:00
Inertial Guidance System Activation
On-Board Recorders activated
L-00:06:00
COUNTDOWN AUTO SEQUENCE
L-00:05:00
Ground & On-Board Telemetry Activation
Transfer to onboard Control
Commander Controls activated
Visors Closed and Air Flow Initiation
Launch Key Inserted in Launch Bunker
L-00:03:15
Engine Nitrogen Purge
L-00:02:40
Umbilical mast power disconnected to 3rd stage
L-00:02:35
Propellant Tank Pressurization
L-00:02:30
Onboard Measurement System Activation
L-00:02:15
Propellant Tank Drain&Safety Valves closed
LOX and N2 Loading Termination
L-00:01:00
Transfer to Internal Power
AUTO SEQUENCER ENABLED
First Umbilical Tower Separates from Booster
L-00:00:40
Power Umbilical to third Stage disconnected
L-00:00:20
ENGINE IGNITION (Core Stage and Boosters)
L-00:00:15
Intermediate Thrust Level
Second umbilical Tower separated from Booster
L-00:00:10
Engine Turbopumps at Flight Speed
L-00:00:05
Full Thrust Level
L-00:00:00
Fueling Tower Retracts
LIFTOFF